Disused Gas Platforms To Be Removed By World’s Largest Vessel

07 Jan 2021

Final preparations for Spirit Energy’s DP3 and DP4 installations to be lifted from the East Irish Sea are underway, and the two 11,000-tonne platforms will be removed by Allseas’ Pioneering Spirit.

The infrastructure used to produce gas as part of Spirit Energy’s complex of eight installations in Morecambe Bay. As the field has matured, the reserves the platforms previously tapped into have been produced by the larger, manned Central Morecambe platform nearby.

The 12 wells which were connected to the DP3 and DP4 platforms have already been plugged and abandoned – using a slant rig to accommodate the angle at which the wells were drilled in the 1980s to access the gas reservoir below the seabed – and the platforms will soon be safe to be lifted and taken back to shore.

Allseas’ 382-metre Pioneering Spirit will lift both the DP3 and DP4 platforms – well within its limits of lifting 48,000-tonne topsides. The infrastructure will then be transferred for recycling to the new facility operated by Cesscon Decom at Fife Energy Park in the UK.

Donald Martin, Project Manager at Spirit Energy, said: “After two years of preparing the DP3 and DP4 installations for removal, we’re now looking forward to one of the most significant milestones in the project with the removal of both platforms.

“Seeing the Pioneering Spirit in the East Irish Sea will be an impressive sight –its capacity and single-lift methodology made it a good fit to safely execute this project."

Comments

Popular posts from this blog

ADNOC’s Sour Gas Hail, Ghasha and Dalma Project Takes Critical Next Step

Axens Awarded Licences For The Saudi Aramco Jazan Refinery & Terminal Project

KazMunayGas and LUKOIL Sign Agreement on Al-Farabi Project