Chiyoda Corporation (“Chiyoda”, TSE: 6366; ISIN: JP3528600004) is pleased to announce that
CSTS, a consortium led by Indonesian EPC Contractor Tripatra with Chiyoda, Saipem and Suluh
Ardhi Engineering, has been awarded a contract by BP Berau Ltd. (as the operator of Berau, Muturi
& Wiriagar Production Sharing Contracts (“Tangguh”)) for the onshore EPC work for Tangguh
Expansion Project (Tangguh LNG Train 3) as detailed below:
1. Client : BP Berau Ltd.
2. Location : Papua Barat, Indonesia
3. Scope : EPC Lump Sum
4. Completion : Fiscal Year 2020
5. Execution Scheme : Consortium of Chiyoda, Tripatra, Saipem and SAE
6. Project Outline :
Tangguh LNG Train 3 with a liquefaction capacity of 3.8 million tons per annum (mtpa) will be
built at the Tangguh site, which is located in Papua Barat Province of Indonesia, in addition to
the existing Train 1 and 2 (3.8 mtpa x 2 Trains).
CSTS will commence execution of the EPC work of Tangguh LNG Train 3 in 2016, which also
encompasses LNG jetty and associated infrastructure
Chiyoda Corporation (“Chiyoda”, TSE: 6366; ISIN: JP3528600004) is pleased to announce that
CSTS, a consortium led by Indonesian EPC Contractor Tripatra with Chiyoda, Saipem and Suluh
Ardhi Engineering, has been awarded a contract by BP Berau Ltd. (as the operator of Berau, Muturi
& Wiriagar Production Sharing Contracts (“Tangguh”)) for the onshore EPC work for Tangguh
Expansion Project (Tangguh LNG Train 3) as detailed below:
1. Client : BP Berau Ltd.
2. Location : Papua Barat, Indonesia
3. Scope : EPC Lump Sum
4. Completion : Fiscal Year 2020
5. Execution Scheme : Consortium of Chiyoda, Tripatra, Saipem and SAE
6. Project Outline :
Tangguh LNG Train 3 with a liquefaction capacity of 3.8 million tons per annum (mtpa) will be
built at the Tangguh site, which is located in Papua Barat Province of Indonesia, in addition to
the existing Train 1 and 2 (3.8 mtpa x 2 Trains).
CSTS will commence execution of the EPC work of Tangguh LNG Train 3 in 2016, which also
encompasses LNG jetty and associated infrastructure